Field notes · October 2026
Open Compute from the grid side: busbars, sidecars, and the first ride-through spec
For most of its life, the Open Compute Project was something server people talked about. That has changed. In the last year OCP has published a ±400 VDC power rack, a solid-state transformer spec, and—in September—a specification for how hyperscale data centers behave at the point of interconnection when the grid faults. If you plan, protect, or interconnect large loads, OCP is now writing documents that land on your desk.
What OCP is (and is not)
OCP is not one standard. It is a foundation, started by Facebook in 2011, that publishes contributed specifications under an open license. A base specification defines an interface several companies agree to build against; a design specification documents one company's implementation of it. Hardware that conforms shows up on the OCP Marketplace, and the working code—firmware, management tools, test suites—lives on GitHub.
The useful mental model for a power engineer: OCP specs are interface agreements between the people who buy the most hardware on earth. They are not IEEE standards and carry no regulatory weight. But when Google, Meta, Microsoft, and NVIDIA sign the same document, it tells you what the equipment at your next interconnection will look like, often two years before it arrives.
The power path, rack to POI
Read the OCP power work as a single path from the chip back to the utility. Each layer has its own specification, and the voltage keeps climbing as rack power does.
| Layer | OCP document | What it pins down |
|---|---|---|
| In-rack DC bus | Open Rack V3 | 48 V-class vertical busbar; power shelf output nominal 51 or 54 VDC; standardized busbar geometry so any vendor's sled mates with any vendor's rack |
| Rack-level backup | ORv3 BBU shelf | Six 3 kW battery modules, 5+1 redundant; about four minutes at 15 kW. The UPS moved into the rack |
| Row-level DC | Mt. Diablo 1.0 (sidecar) | 480/415/400 VAC in, ±400 VDC (or differential 800 VDC) out; 800 kW to 1.1 MW per power rack at 480 VAC; battery (45–90 s at full load) or capacitor-bank storage |
| Facility conversion | SST spec v0.3, LVDC white paper | Medium voltage directly to 800 VDC; the data hall stops being an AC distribution problem |
| Point of interconnection | Disturbance performance spec v1.0.0 | Voltage ride-through and post-fault active power recovery for the computational load |
The driver is arithmetic. The Mt. Diablo spec frames its own scope as rack power moving “from 33kW to 100's of kW.” At 48 V, a megawatt is more than 20,000 amps of busbar. At ±400 V it is a cable you can actually route. Mt. Diablo pulls the AC-DC conversion, protection, and energy storage out of the IT rack into a neighboring power rack, so the compute rack can stay the same while the power rack scales—and gets swapped—on its own schedule.
Two details worth noticing as a protection engineer. First, Mt. Diablo spends real pages on mid-point grounding of the ±400 VDC bus versus grounding for differential 800 VDC—DC fault detection and clearing in a data hall is a problem the industry has not had at this scale before. Second, it requires that battery backup not be triggered during peak or dynamic loading. The storage is there for the grid, not for the GPUs' bad moods.
Why the grid-side spec exists: three events in Virginia
On July 10, 2024, a lightning arrester failure on a 230 kV line in the Eastern Interconnection produced a normally cleared fault. Nothing at the utility tripped. But the line's reclosing sequence produced several voltage dips in a short window, and data center protection schemes that count voltage disturbances decided the grid was unhealthy and transferred roughly 1,500 MW of load to backup power. Frequency and voltage rose; operators pulled shunt capacitors to bring voltage back. NERC's incident review is short and worth reading in full.
The follow-up is the encouraging part. Data center operators lengthened the time a dip must last to be “counted” and changed how many dips trigger transfer. On April 18, 2026, a fault in the same vicinity with similar characteristics cost only about 500 MW. Then, in July 2026, a customer-initiated load reduction of nearly 4 GW occurred in Virginia; NERC says it is still under analysis. Generation-loss events have Reliability Standards for ride-through. Simultaneous load loss of this size was not something planners were designing for, and every data center on a circuit sees the same disturbance at the same instant—a textbook common-mode failure.
What the OCP disturbance spec actually commits to
The Interface Specification Between Hyperscalers and Utility Grid for Disturbance Performance (v1.0.0, effective September 17, 2026) is authored by Google, Meta, Microsoft, and NVIDIA. It adopts MISO's convention, closely mirrors ERCOT's NOGRR 282, and applies at the POI regardless of connection voltage. Here is the core table:
| POI voltage (p.u.) | Min. ride-through before transfer to backup | Load behavior during ride-through | Recovery once 0.90 ≤ V ≤ 1.10 |
|---|---|---|---|
| V > 1.20 | May transfer instantaneously | — | — |
| 1.10 < V ≤ 1.20 | 1.0 s | Maintain constant power | — |
| 0.90 ≤ V ≤ 1.10 | Continuous | Maintain constant power | — |
| 0.80 ≤ V < 0.90 | 2.0 s | Keep consuming; may reduce in proportion to V | 90% of pre-fault load within 2 s |
| 0.50 ≤ V < 0.80 | 0.5 s | Keep consuming; may reduce in proportion to V | 90% of pre-fault load within 2 s |
| 0.35 ≤ V < 0.50 | 0.25 s | May reduce to any value | 90% of pre-fault load within 2 s |
| V < 0.35 | 0.15 s | May reduce to any value | 90% of pre-fault load within 2 s |
Summarized from Table 1 of the OCP specification. Read the source before using it in a study.
What a planner should take from it:
- It covers the computational load only—which the spec puts at roughly 70–90% of the facility. Cooling is explicitly exempt. Chillers and pumps sit behind VFDs commonly set per IEEE 1566 (which typically allows shutdown below 0.65 p.u. for over 500 ms), can take minutes rather than seconds to restart, and come from too many OEMs for a firmware fix. ERCOT handles this by subtracting tripped cooling load from the pre-fault baseline. Your dynamic model should have two load components, not one.
- Below 0.5 p.u., it is momentary cessation for loads. Power may go to zero as long as 90% comes back within two seconds. The authors are blunt that true ride-through at 0 p.u. would need more capacitance in every PSU—and the inrush on recovery could then breach current limits that ERCOT and EirGrid impose. Anyone who lived through inverter-based resource momentary cessation will recognize the shape of this tradeoff.
- The fix is mostly PSU firmware. Rack rectifiers can use their own stored energy to hold the curve, but feasibility is OEM- and model-specific. MV-UPS retrofits are described as generally too costly to be practical. The spec also suggests utilities consider SVCs and E-STATCOMs in data center clusters to make the sag shallower in the first place.
- The thing that caused July 2024 is still future work. Counter-based protection schemes, frequency ride-through, rate of change of frequency, phase jump, ramp rates, and forced oscillations are all listed as items for a later version. The spec also asks utilities to standardize transmission reclosing practice, since fast reclosing can look like one long fault to a data center's protection.
- Grandfathering is proposed, not settled. Facilities operating or holding executed interconnection agreements as of an effective date would be exempt for life; only incremental load at existing sites would have to comply. Expect that to be argued over in every jurisdiction that writes its own rule.
The next problem: loads that oscillate on purpose
Ride-through is about faults. The harder long-term issue is normal operation. Large AI training jobs alternate between compute-heavy and communication-heavy phases in lockstep across thousands of GPUs, so the whole facility's demand swings together. Microsoft, OpenAI, and NVIDIA laid this out in Power Stabilization for AI Training Datacenters, along with the mitigation stack: software that fills the idle phases, GPU-level power floors and ramp limits, and energy storage at the rack.
That is the context for the capacitor-bank option in Mt. Diablo and for the OCP 800 VDC work explicitly listing power smoothing alongside power quality as a standards target. It is also why the disturbance spec names forced oscillations as future work. When that version lands, it will be the first time a load-side standards body has told the grid how fast its loads are allowed to move.
Using OCP on an interconnection
If you are on the utility or EOR side of a large-load study, OCP gives you a vocabulary for questions you should already be asking:
- Which rack and power architecture: 48 V ORv3, a ±400 VDC sidecar, or MV-to-DC? It changes the load model.
- Will the computational load meet the OCP disturbance table, and with what PSU firmware revision? Who controls that firmware after commissioning?
- What does the cooling plant do below 0.65 p.u., and how long does it take to come back?
- What are the voltage-disturbance counter settings on the transfer scheme—count window, dip duration, trip count?
- Is there rack- or row-level storage, and is any of it configured for power smoothing rather than backup?
Those answers belong in the study sequence long before commissioning. NERC's large-loads white paper is on our Resources page.
Open these tabs
The primary documents behind this note, plus a few worth having bookmarked. Links open the source directly.
Grid interface
- Interface Specification Between Hyperscalers and Utility Grid for Disturbance Performance v1.0.0 ↗OCP · Google, Meta, Microsoft, NVIDIA · Sept 2026
The ride-through table, the cooling-load carve-out, and a proposed grandfathering scheme. Section 4.4.4 is the candid part.
- Incident Review: Considering Simultaneous Voltage-Sensitive Load Reductions ↗NERC
The July 2024 event: a 230 kV fault, normal reclosing, and ~1,500 MW of data center load transferring itself to backup.
- Reliability Insights: Large Computational Load Risks Due to Voltage Sensitivity ↗NERC · Sept 2026
Four pages. The April 2026 repeat fault (only 500 MW lost after protection changes) and the ~4 GW July 2026 event.
- Large Load Performance Requirements: Current Practices and Recommendations ↗ESIG Large Loads Task Force · 2026
The best survey of what utilities are actually asking for; the OCP spec leans on it heavily.
- NOGRR 282 ↗ERCOT
The ERCOT ride-through language the OCP table most closely mirrors, including how cooling load is excluded from recovery.
Power delivery: rack to row
- Mt. Diablo Disaggregated Power Rack Specification v1.0.0 ↗OCP · Microsoft, Meta, Google · Oct 2026
The ±400 VDC sidecar. AC input tables, DC output tolerances, BBU and capacitor-bank storage, and mid-point grounding.
- Solid State Transformer (SST) Specification v0.3 ↗OCP · Google, Microsoft, NVIDIA · 2026
Medium voltage straight to 800 VDC. Early, but it is where the facility one-line is heading.
- Low Voltage DC (LVDC) Power Distribution White Paper v1.0 ↗OCP Data Center Facility project
The architecture overview behind the 800 VDC push: side power racks versus MV-to-DC conversion.
- Why Scaling AI Compute Performance Requires a New Power Architecture ↗NVIDIA
The vendor case for 800 VDC, from the company whose racks are forcing the issue.
The rack itself
- Open Rack V3 Base Specification Rev 1.1 ↗OCP
The 48 V busbar rack most OCP hardware still lands in. Busbar geometry and the 51/54 VDC nominal options.
- Open Rack V3 BBU Shelf Rev 1.1 ↗OCP · Meta
Six 3 kW battery modules, 5+1, roughly four minutes at 15 kW. The UPS, moved into the rack.
- Open Rack Wide (ORW) Base Specification v1.0.1 ↗OCP · Meta
The double-width rack built for the densest accelerator platforms.
- Rack & Power: Specs and Designs index ↗OCP wiki
Every rack and power contribution in one list, from ORv1 PDUs to HPR 72 kW shelves. Bookmark this one.
Load behavior and cooling
- Power Stabilization for AI Training Datacenters ↗Microsoft, OpenAI, NVIDIA · arXiv 2508.14318
Why synchronized training jobs swing power, and the software, GPU, and rack-storage options for smoothing it.
- ACS Liquid Cooling Cold Plate Requirements ↗OCP
Technology cooling system loop pressures, CDU options, and the spill-management plan nobody wants to write.
- Characteristics and Risks of Emerging Large Loads ↗NERC Large Loads Task Force · July 2025
The planning, operations, and stability framing utilities are now working from.
Code and silicon
- Open Compute Project on GitHub ↗github.com/opencomputeproject
Firmware, management tooling, and test suites. The specs are PDFs; this is where the working code lives.
- Caliptra ↗CHIPS Alliance · OCP-originated
Open silicon root of trust. Relevant once you start asking who can push firmware to the PSUs doing your ride-through.
Educational overview, not engineering guidance. OCP specifications are voluntary industry agreements, not interconnection requirements; your utility's rules govern. Figures are from the cited documents as of October 2026—check for newer revisions before relying on them.
